1415PERFORMANCE REPORT The Water Boards...

State Water Board Logo

The California Water Boards' Annual Performance Report - Fiscal Year 2014-15

State Board | Region 1 | Region 2 | Region 3 | Region 4 | Region 5 | Region 6 | Region 7 | Region 8 | Region 9

TARGETS AND RESOURCES: REGION 4 LOS ANGELES


GROUP:  TARGETS AND RESOURCES - REGION 4 MEASURE: ALL REGIONAL TARGETS
ALL RESOURCES

Targets Achieved:
= Less than 60% of target met
= Target met between 60% and 80%
= Target met at 80% or above

Los Angeles Regional Water Board Performance Summary1
Percentage of Targets Met
Area: 4451 square miles Budget: $21,069,429 Staff: 141
Permitting 100% Inspections 100% Others 100%
1Regional Board performance summary statistics show the percentage of targets met.
 
Total Maximum Daily Load and Basin Planning
Program Budget: $1,765,832 Program Staff: 12.70
  Target Actual Achieved % of Targets Met
Pollutant/Water Body Combinations Addressed 8 12 150%
Total Maximum Daily Loads Adopted 5 5 100%
Basin Plan Amendments Adopted 3 5 167%
No Regional Considerations Provided
NPDES Wastewater
Program Budget: $2,711,560 Program Staff: 18.90
  Target Actual Achieved % of Targets Met
Major Individual Permits Issued or Renewed 11 11 100%
Major Individual Facilities Inspected 23 28 122%
Minor Individual Permits Issued or Renewed 11 12 109%
Minor Individual Facilities Inspected 12 20 167%
Minor General Facilities Inspected 40 101 253%
No Regional Board Considerations Provided
NPDES Stormwater
Program Budget: $1,882,713 Program Staff: 14.50
  Target Actual Achieved % of Targets Met
Municipal (Phase I/II Inspections) 5 7 140%
Construction Inspections 170 412 242%
Industrial Inspections 160 345 216%
No Regional Board Considerations Provided
Waste Discharge to Land - Wastewater
Program Budget: $827,477 Program Staff: 4.50
  Target Actual Achieved % of Targets Met
Waste Discharge to Land Inspections 24 36 150%
Individual Waste Discharge Requirements Issued or Updated 5 7 140%
No Regional Considerations Provided
Land Disposal
Program Budget: $502,757 Program Staff: 3.50
  Target Actual Achieved % of Targets Met
Landfill Individual Permits Issued or Updated 3 5 167%
Landfill Inspections 34 42 124%
Land Disposal All Other Individual Permits Issued or Updated 1 5 500%
Land Disposal All Other Inspections 26 22 85%
No Regional Considerations Provided
Confined Animal Facilities (WDR, NPDES, etc.)  
Program Budget: $0 Program Staff: 0.00
  Target Actual Achieved % of Targets Met
Confined Animal Facilities Inspections 0 0  
No Regional Considerations Provided
Timber Harvest (Forestry)  
Program Budget: $0 Program Staff: 0.00
  Target Actual Achieved % of Targets Met
Timber Harvest Inspections 0 0  
No Regional Considerations Provided
Enforcement
Program Budget: $952,030 Program Staff: 7.70
  Target Actual Achieved % of Targets Met
Class 1 Priority Violations will Result in Formal Enforcement or an Investigative Order Pursuant to Water Code Section 13267 within 18 Months of Discovery 100% 100% 100%
Facilities with Over $12,000 in MMPs (4 or More Violations) Not Assessed within 18 Months of Accrual 0 0        
No Regional Board Considerations Provided
Cleanup
Program Budget: $6,831,573 Program Staff: 47.30
  Target Actual Achieved % of Targets Met
New Department of Defense Sites Into Active Remediation 2 15 750%
New Cleanup Sites Into Active Remediation 10 43 430%
Cleanup Sites Closed 12 214 1,783%
New Underground Storage Tank Sites Into Active Remediation 12 45 375%
Underground Storage Tank Sites Projected Closed 120 124 103%
No Regional Considerations Provided

 

 

RESOURCES (INPUTS)

 

 

WHAT THE CARD IS SHOWING

Each target card provides a direct comparison of actual outputs for the fiscal year (July 1st to June 30th) to the target estimates established at the outset of the fiscal year. While budgetary and personnel information is not directly aligned with the activities being assessed, it does provide a basis for understanding the relative priority of key programs within each region and across the State. For the actual outputs presented, the Water Boards are continuing to evolve its data bases for improved accuracy. Some of the measurements reported may be different than the measurements tracked by the regions and programs. In addition, there are several targets for which outputs cannot be readily displayed without modification to the databases. This includes the number of permits revised, which should include the number of permits reviewed, revised and/or rescinded.

For the actual outputs presented, the Water Boards are continuing to evolve its data bases for improved accuracy. Some of the measurements reported may be different than the measurements tracked by the regions and programs. Notably, the data portrayed include entries completed before November 4, 2014 and may not reflect data input after that period.

WHY THIS CARD IS IMPORTANT

Beginning with FY 2009-10, performance targets were established for certain output measures. Targets are goals that establish measurable levels of performance to be achieved within a specified time period. This card demonstrates how the resources of the region are being deployed to protect water quality. In establishing the targets, the Regional Water Boards considered the unique differences and needs within their respective watersheds, their work priorities given available resources, external factors such as furloughs, and prior year outputs.

TECHNICAL CONSIDERATIONS

  • Target circles: = Less than 60% of target met
    = Target met between 60% and 80%
    = Target met at 80% or above.
  • Other Programs (budget): miscellaneous programs not included in the above.
  • Permits issued: Does not include rescissions, amendments or permit revisions that may have been included in the targets.

REGIONAL CONSIDERATIONS

Regional Considerations provided in tables above under each program section.

( Page last updated:  6/2/15 )

 
 

.
Region 4 (Los Angeles) FY 14-15
Budget ($)
Staff (PY) %Fees/Taxes
Penalties
%Federal %General
Fund/Other
%Bonds