RESOLUTION NO. 99 – 096

 

APPROVAL OF A STATE REVOLVING FUND (SRF) LOAN FOR

TREATMENT PLANT, STORAGE, AND DISPOSAL IMPROVEMENTS

BODEGA BAY PUBLIC UTILITY DISTRICT

SRF LOAN PROJECT NO C-06-4615-110

 

 

WHEREAS:

 

1. The State Water Resources Control Board (SWRCB), on February 16, 1995, adopted the “Policy for Implementing the State Revolving Fund (SRF) for Construction of Wastewater Treatment Facilities,” and amended it on June 18, 1998;

 

2. The SWRCB, on June 17, 1999, adopted the FFY 2000 SRF Loan Program Priority List which included the Treatment Plant, Storage, and Disposal Improvement Project, Bodega Bay Public Utility District (District) in Priority Class C;

 

3. The Division of Clean Water Programs (Division) has approved the project report, environmental documents, and draft revenue program, for the Treatment Plant, Storage, and Disposal Improvement Project;

 

4. The District adopted a Mitigated Negative Declaration/Initial Study and a Subsequent Mitigated Negative Declaration (State Clearinghouse No. 98122014) for the proposed project, which have been reviewed and considered, and it has been determined that the proposed project will not result in any significant negative environmental impacts; and

 

5. The District is not subject to the water conservation requirements because it serves less than 3,000 customers and supplies less than 3,000 acre-feet of water annually to the customers.

 

THEREFORE BE IT RESOLVED THAT:

 

The State Water Resources Control Board:

 

1. Approves a SRF loan of $1.9 million from the SFY 2000-01 account to the Bodega Bay Public Utility District for construction of the Treatment Plant, Storage, and Disposal Improvement Project, with a repayment period of 20 years, and the first repayment due one year after completion of construction; and

 

2. Will withdraw this preliminary SRF loan commitment if project construction is not initiated by June 1, 2000. The Division may approve up to a 90-day extension for good cause.

 

CERTIFICATION

 

The undersigned, Administrative Assistant to the Board, does hereby certify that the foregoing is a full, true, and correct copy of a resolution duly and regularly adopted at a meeting of the State Water Resources Control Board held on October 21, 1999.

 

/s/

Maureen Marché

Administrative Assistant to the Board

 
 

.