Ocean Standards - CWA §316(b) Regulation
Cooling Water Intake Structures
Once-Through Cooling Water Policy - Interim Mitigation Measures
The State Water Resources Control Board (State Water Board) Statewide Water Quality Control Policy on the Use of Coastal and Estuarine Waters for Power Plant Cooling (Once-Through Cooling or OTC Policy) requires owners or operators of existing power plants to implement measures to mitigate interim impingement and entrainment impacts resulting from their cooling water intake structures. The interim mitigation period commenced on October 1, 2015, and continues up to and until owners or operators achieve final compliance with the OTC Policy. Section 2.C.3 of the OTC Policy provides information for demonstrating compliance with the interim mitigation. Resolution No. 2015-0057 (2015 Resolution) describes the procedures for calculating the mitigation payment. The State Water Board calculates the interim mitigation payments by summing three components: an entrainment payment, an impingement payment, and a management and monitoring payment.
The State Water Board calculates interim mitigation payments annually, based on data and information provided by the power plant owners and operators. The State Water Board provides letters with the calculated annual interim mitigation payment and instructions for the payment process. When appropriate, the State Water Board prepares draft determinations for mitigation measures on a case-by-case basis. Consistent with the 2015 Resolution, draft determinations are posted for a public comment period of 20 days and circulated to persons who have requested public notice on matters related to the OTC Policy. After considering the public comments received on a draft determination, the Executive Director shall consider whether, in light of unusual circumstances or significant controversy, the final approval of the determination should be made by the State Water Board at a public meeting.
News!
- On April 17, 2024, the State Water Resources Control Board will consider adopting a Revised Draft Resolution to revise the interim mitigation payment calculation for the Water Quality Control Policy on the Use of Coastal and Estuarine Waters for Power Plant Cooling and Proposed Final Staff Report. For additional meeting details, please see the public notice.The Revised Draft Resolution, Proposed Final Staff Report, and Responses to Comments can be found in the “Revision to Interim Mitigation Payments Calculation” section below.
Public Meetings
Consideration of Adoption for the Resolution to Revise the Interim Mitigation Payment Calculation for the
Water Quality Control Policy on the Use of Coastal and Estuarine Waters for Power Plant Cooling
Wednesday, April 17, 2024, at 9:00 am
COASTAL HEARING ROOM
Joe Serna Jr. – CalEPA Headquarters Building
1001 I Street, Second Floor
Sacramento, CA 95814
And via Video and Teleconference
For additional details, please see the public notice.
Final Determinations Approving Interim Mitigation Measures
- Alamitos Generating Station:
- 21-22 Final Determinations and Invoice Letter for Alamitos Generating Station – February 27, 2024
- 20-21 Final Determinations and Invoice Letter for Alamitos Generating Station – December 30, 2022
- 19-20 Final Determination and Invoice Letter for Alamitos Generating Station – January 18, 2022
- 18-19 Final Determination and Invoice Letter for Alamitos Generating Station – October 20, 2020
- 17-18 Final Determination and Invoice Letter for Alamitos Generating Station – September 9, 2019
- 16-17 Final Determination and Invoice Letter for Alamitos Generating Station - July 25, 2018
- 15-16 Final Determination and Invoice Letter for Alamitos Generating Station posted December 11, 2017
- Responses to Comments posted January 29, 2018
- Diablo Canyon Nuclear Power Plant:
- 21-22 Final Determinations and Invoice Letter for Diablo Canyon Nuclear Power Plant – February 27, 2024
- 20-21 Final Determinations and Invoice Letter for Nuclear Canyon Nuclear Power Plant – December 30, 2022
- 19-20 Final Determination and Invoice Letter for Diablo Canyon Nuclear Power Plant – January 14, 2022
- 18-19 Final Determination and Invoice Letter for Diablo Canyon Nuclear Power Plant – October 20, 2020
- 17-18 Final Determination and Invoice Letter for Diablo Canyon Nuclear Power Plant – September 9, 2019
- 16-17 Final Determination and Invoice Letter for Diablo Canyon Nuclear Power Plant - July 25, 2018
- 15-16 Final Determination and Invoice Letter for Diablo Canyon Nuclear Power Plant - posted December 12, 2017
- Responses to Comments - posted December 12, 2017
- Encina Power Station:
- 17-18 Final Determination and Invoice Letter for Encina Power Station – September 9, 2019
- 16-17 Final Determination and Invoice Letter for Encina Power Station - July 25, 2018
- 15-16 Final Determination and Invoice Letter for Encina Power Station - posted March 14, 2018
- Final Determination for Encina Power Station - posted February 16, 2017
- Responses to Comments
- El Segundo Generating Station:
- 15-16 Final Determination for El Segundo Generating Station - posted March 1, 2016
- Harbor Generating Station:
- 21-22 Final Determinations and Invoice Letter for Harbor Generating Station – February 27, 2024
- 20-21 Final Determinations and Invoice Letter for Harbor Generating Station – December 30, 2022
- 19-20 Final Determination and Invoice Letter for Harbor Generating Station – January 14, 2022
- 18-19 Final Determination and Invoice Letter for Harbor Generating Station – October 20, 2020
- 17-18 Final Determination and Invoice Letter for Harbor Generating Station – September 9, 2019
- 16-17 Final Determination and Invoice Letter for Harbor Generating Station - July 25, 2018
- 15-16 Final Determination and Invoice Letter for Harbor Generating Station - posted December 11, 2017
- Responses to Comments - posted January 29, 2018
- Haynes Generating Station:
- 21-22 Final Determinations and Invoice Letter for Haynes Generating Station – February 27, 2024
- 20-21 Final Determinations and Invoice Letter for Haynes Generating Station – December 30, 2022
- 19-20 Final Determination and Invoice Letter for Haynes Generating Station – January 14, 2022
- 18-19 Final Determination and Invoice Letter for Haynes Generating Station – October 20, 2020
- 17-18 Final Determination and Invoice Letter for Haynes Generating Station – September 9, 2019
- 16-17 Final Determination and Invoice Letter for Haynes Generating Station - July 25, 2018
- 15-16 Final Determination and Invoice Letter for Haynes Generating Station - posted December 11, 2017
- Responses to Comments - January 29, 2018
- Huntington Beach Generating Station:
- 21-22 Final Determinations and Invoice Letter for Huntington Beach Generating Station – February 27, 2024
- 20-21 Final Determinations and Invoice Letter for Huntington Beach Generating Station – December 30, 2022
- 19-20 Final Determination and Invoice Letter for Huntington Beach Generating Station – January 19, 2022
- Responses to Comments – posted January 27, 2022
- 18-19 Final Determination and Invoice Letter for Huntington Beach Generating Station – October 20, 2020
- 17-18 Final Determination and Invoice Letter for Huntington Beach Generating Station – September 9, 2019
- 16-17 Final Determination and Invoice Letter for Huntington Beach Generating Station - July 25, 2018
- 15-16 Final Determination for Huntington Beach Generating Station - posted January 29, 2018
- Responses to Comments - posted January 29, 2018
- Mandalay Generating Station:
- 16-17 Final Determination and Invoice Letter for Mandalay Generating Station - July 25, 2018
- 15-16 Final Determination and Invoice Letter for Mandalay Generating Station - posted December 11, 2017
- Responses to Comments - posted January 28, 2018
- Ormond Beach Generating Station:
- 21-22 Final Determinations and Invoice Letter for Ormond Beach Generating Station – February 27, 2024
- 20-21 Final Determinations and Invoice Letter for Ormond Beach Generating Station – December 30, 2022
- 19-20 Final Determination and Invoice Letter for Ormond Beach Generating Station – January 14, 2022
- 18-19 Final Determination and Invoice Letter for Ormond Beach Generating Station – October 20, 2020
- 17-18 Final Determination and Invoice Letter for Ormond Beach Generating Station – September 9, 2019
- 16-17 Final Determination and Invoice Letter for Ormond Beach Generating Station - July 25, 2018
- 15-16 Final Determination and Invoice Letter for Ormond Beach Generating Station - posted December 11, 2017
- Redondo Beach Generating Station:
- 21-22 Final Determinations and Invoice Letter for Redondo Beach Generating Station – February 27, 2024
- 20-21 Final Determinations and Invoice Letter for Redondo Beach Generating Station – December 30, 2022
- 19-20 Final Determination and Invoice Letter for Redondo Beach Generating Station – January 18, 2022
- 18-19 Final Determination and Invoice Letter for Redondo Beach Generating Station – October 20, 2020
- 17-18 Final Determination and Invoice Letter for Redondo Beach Generating Station – September 9, 2019
- 16-17 Final Determination and Invoice Letter for Redondo Beach Generating Station - July 25, 2018
- 15-16 Final Determination and Invoice Letter for Redondo Beach Generating Station - posted December 11, 2017
- Responses to Comments - posted January 29, 2018
- Scattergood Generating Station:
- 21-22 Final Determinations and Invoice Letter for Scattergood Generating Station – February 27, 2024
- 20-21 Final Determinations and Invoice Letter for Scattergood Generating Station – December 30, 2022
- 19-20 Final Determination and Invoice Letter for Scattergood Generating Station – January 14, 2022
- 18-19 Final Determination and Invoice Letter for Scattergood Generating Station – October 20, 2020
- 17-18 Final Determination and Invoice Letter for Scattergood Generating Station – September 9, 2019
- 16-17 Final Determination and Invoice Letter for Scattergood Generating Station - July 25, 2018
- 15-16 Final Determination and Invoice Letter for Scattergood Generating Station - posted December 11, 2017
Annual Reports – Use of Interim Mitigation Funds
Most owners and operators elected to comply with interim mitigation requirements via Sections 2.C(3)(b) and 2.C(3)(e) of the OTC Policy. Section 2.C(3)(b) directs interim mitigation funds to be paid to the Ocean Protection Council (“OPC”) and State Coastal Conservancy (“Conservancy”) to fund appropriate mitigation projects. Section 2.C(3)(e) of the OTC Policy states that it is the preference of the State Water Board that funding is provided to the Conservancy, working with the OPC, for mitigation projects directed toward increases in marine life associated with the State’s Marine Protected Areas (MPA) in the geographic region of the facility, including restoration of wetlands. Mitigation projects are defined in the OTC Policy as projects to restore marine life lost through impingement mortality and entrainment, and may include projects to restore and/or enhance coastal marine or estuarine habitat, and may also include protection of marine life in existing marine habitat, for example through the funding of implementation and/or management of MPAs. Projects that the OPC funds with interim mitigation payments are intended to support and protect the MPA network.
In accordance with the 2016 Memorandum of Agreement entered into by the State Water Board, the OPC, and the Conservancy (2016 MOU), the State Water Board participates in the selection process and approves of appropriate mitigation projects. Section 8 of the 2016 MOU states that the OPC and the Conservancy will each produce an annual report to the State Water Board identifying each completed mitigation project and the monitoring and maintenance activities that have occurred on each project which requires continued monitoring and maintenance.
- Ocean Protection Council
- State Coastal Conservancy
Delegation of Authority
- Delegation of Authority to the Executive Director, Regarding Approval of Interim Mitigation
- Adopted Resolution 2015-0057
- State Water Board Meeting on August 18, 2015
State Water Board-Contracted Expert Review Panel II on Intake Impacts and Mitigation
The State Water Board contracted with the Moss Landing Marine Laboratory to establish an expert panel to address issues associated with minimizing and mitigating intake impacts from power plants and desalination facilities. The panel members were Dr. Michael Foster, Dr. Greg Cailliet, Dr. Jim Callaway, Dr. Pete Raimondi, and Mr. John Steinbeck. The panel met on August 8, 2011 and on November 15, 2011. A public meeting was held March 1, 2012 at the Moss Landing Marine where panel members presented their recommendations and took questions and comments from the public on the panel’s Draft Report. Updates were given on the other two studies. The panel members deliberated and made changes to their report, which was finalized on March 14, 2012.
- Expert Review Panel II on Intake Impacts and Mitigation
Revision to Interim Mitigation Payments Calculation
The State Water Board is considering revising the interim mitigation payment calculation, which was established in 2015 through the adoption of Resolution No. 2015-0057. The proposed revision will update the costing multipliers used to calculate the entrainment and impingement payments, and the annual inflation escalator approach. The revision to the interim mitigation calculation will ensure that annual payments continue to appropriately compensate for interim impacts to marine life based on current mitigation costs.
- Technical Documents
- Revised Draft Resolution (April 4, 2024)
- Proposed Final Staff Report (April 4, 2024)
- Responses to Comments (April 4, 2024)
- Draft Resolution (September 27, 2023)
- Staff Report (September 27, 2023)
- 2023 Expert Review Report by Dr. Pete Raimondi (September 27, 2023)
- Notices
- Fact Sheet (August 21, 2023)
Documentos en Español
- Aviso Modificado (14 de septiembre de 2023)
- Aviso: Audiencias Públicas, Disponibilidad de documentos, y oportunidad para comentarios públicos (18 de agosto de 2023)
- Información de Actualización (21 de agosto de 2023)
Questions or Comments
- Permitting Issues - Renan Jauregui at (916) 341-5505 or by email at Renan.Jauregui@waterboards.ca.gov
- Policy Issues - Kat Faick at (916) 445-2317 or by email at Kat.Faick@waterboards.ca.gov or Jonathan Dolan at (916) 323-0880 or Jonathan.Dolan@waterboards.ca.gov